This paper is to estimate the Economic Value of the Placer Mining Industry.  There is not a lot of documentation, especially the small scale miner. This group generally works in semi isolation.  There are several classifications within this group depending on the degree of mechanization.  It is very common for a miner to progress through the various phases increasing his economic contribution.

 

Hand Mining

As the name implies uses manual tools, sorting aggregate and separating the mineral in a sluice box or high-banker.  A small pump is usually the only mechanical component. This method is labor intensive but an economical way to process material.

 

Mechanized Mining

This is where the Backhoes, Excavators and wash plants come in. This is the entry level for larger mining ventures.  The type of equipment required is tied to the specifics of the site, De-Rockers to size the aggregate, Trommels to break up clay and compacted material, Sluice boxes to separate the heavy gold from the light material, Jigs and Sorting Tables to retrieve the fine gold. This classification can expand to the limits of ones imagination and the size of the deposit.

 

Size of the Industry

There are today 3500 Placer Claims covering 237,000 hectares and 275 Placer Leases covering 290,900 hectares.  Revenue paid to government for acquiring and holding placer titles last year was over $2.2 Million (See Table 3 Lines 1-4 for calculation of estimate).

 

Last year 179 permits were issued under the Mines Act for mechanized placer work.  I have assumed the majority 134 permits (75%) were issued for leases as they are most likely to have mechanized operations.  That leaves 45 claims doing mechanized work and the balance, 3,455 claims doing their basic assessment work requirement of $500 per legacy claim and $10 per hectare for grid claims. 

 

The Ministry of Mines has records detailing larger operations on leases; I am going to concentrate this report on the value of the remainder.  However, I’ve estimated the economic value of both leases and claims to provide a complete picture of placer activity in the Province.

 

I’ve divided placer operations into four categories in order to develop a more realistic view as to the scope of this industry:

 

  1. Small operation on a claim or lease where 1 person works hand panning and sluicing for about 4 days.
  2. Medium operation on a claim or lease where 2 people hand pan but mostly sluice for about 14 days.  Travel and accommodation costs may be involved as well as a modest investment in a pump and sluicing device.
  3. Long Term operation on a claim or lease where 4 people work 14 days mostly shoveling into a sluice and hand digging, moving rocks and stumps to expose new deposits.  The investment in equipment is more substantial and there is likely travel and accommodation cost involved.  For example the Oregon DEQ identified a couple spent about $2000 for a 2 week mining venture plus the cost of equipment and maintenance.
  4. Mechanical Operation where 6 workers use mechanical equipment to excavate placer material for 30 days in a year and use a mechanized sluicing device.  Travel and accommodation costs are involved.   The FEIR Report makes reference to such an operation on page 68, where expenses were noted as $9, 250.

 

Economic Benefits from Placer Mining:

 

I’ve used three methods to estimate the economic activity of placer in the Province for comparison.  Facts and assumptions used to calculate these estimates are noted in Table 1 and 2, attached.  Each Estimate includes the Title revenue component of $2.2 Million:

1.      Work Requirement:  The Mineral Tenure Act calls for $10 per hectare of exploration and development work to be performed on a placer claim each year.  Also, I’ve made the reasonable assumption that $10 per hectare would also measure work performed on leases each year.

2.      Operational Categories:  I’ve divided the industry into four operational categories noted above and assumed the cost of accommodation, travel, equipment and operating cost for each category for both claim and lease.

3.      Process Cost:  I’ve calculated the cost to excavate overburden, extract pay-dirt and process it according to the operational categories used in Estimate number 2 above.

 

The following table provides a summary of the three methods used to estimate the economic value of placer mining in the Province:

 

           

 

 

The Future and Potential

The Placer Industry has been kept to its knees by ongoing restrictive regulation. With the production limit of 2000 cu meters on a claim, there is a reluctance to ramp up to the potential of the property because that limit can be reached in a few weeks. The upfront costs and delay of converting to a lease is a further aggravation. In some areas the belief that a lease is a lesser title has also caused resistance. This has caused a “Holding Property” scenario were claim holders are waiting for the glimmer of hope that they can start producing in the manner they should. The failure of applying the 2 zone system has also excluded vast areas of the province to exploration. The growing need for the platinum groups will only be met by increased Placer exploration. In the Interior with the massive cull of bug kill trees there will be a severe economic downturn when this project is complete. There needs to be an alternative in place when that time comes and Placer is a prime candidate.

 

The action of the Government in changing the method of staking has resulted in a marked growth in activity.

 

Changes that would make dramatic changes in the economic Viability of Placer are:

  • Removal of production limits and the requirement to convert to Leases. The change to cells has removed the need for a survey of the claims location.
  • Removal of the Placer Reserves. There are vast areas that are known deposits that are out of reach for mining. These areas need to be explored and assessed for economic value.
  • Allow suction dredging to be used in the stream subject to operating agreements negotiated with government agencies.

 

Improvements for the entry level miner

As with every Trade there is a learning curve, Placer Mining is no different. Most start with a gold pan and a shovel, then a basic sluice box, followed with a pump. Now they have to learn about controlling dirty water, building containment and settling areas. The suction dredge removes a lot of the shoveling and increases productivity and more gold. The entry level miner generally spends more than he produces, much like sports fishing. This is the cost of experience. At this time hand mining is pan and shovel, all other methods are not acknowledged. This is causing a break in the creation of the next generation of miners. By allowing power sluices, hydraulic concentrators, and various self contained versions of this equipment to be used by the Hand Miner, he will be encouraged to advance in his venture.

 


Placer Economic Report Tables 1-4.

 

Placer Industry Related Items Placer Claims Placer Leases All Placer Titles Data Source and Estimate Details
 Placer Titles 3,500 275 3,775 Mineral Titles Statistic from MTO
 Hectares held as Placer Title in 2005 237,000 290,900 527,900 Mineral Titles Statistic from MTO
Recording Fee for Work Hectare/Year $2     MTA Regulations Schedule B, Item 8
Cash in Lieu for work/ Hectare/Year $2     MTA Regulations Schedule B, Item 9
 Work Required for a Claim/Hectare/Year $10     MTA Regulations, Section 8, 5
Placer Lease Rental/Hectare/Year   $5   MTA Regulations Schedule B, Item 15
Cost/Hour/Labourer Working on Placer Title $20     Mineral Titles Info Letter No 19, p 2 (Claims).
Permits Issued for Mechanical Operations     179 Mining Division, Mines Act, Section 10
       
TABLE 2 - ASSUMPTIONS USED TO CALCULATE ECONOMIC ACTIVITY OF PLACER INDUSTRY        
Title Revenue       Basis of Assumption
Estimated Revenue From Cash in Lieu Payments in 2005 $250,000     Survey shows less than 30% Pay Cash in Lieu
Estimated Revenue to MTO for recording Miscellaneous Documents in 2005 $50,000 $12,000 $62,000 Includes Transfers, Encumbrances & Miscelaneous Documents
Estimated Work Performed on a Placer Lease/Hectare/Year   $10   Assume work volume on Lease equivalent or more than on a claim
Title Size Estimates        
Estimated proportion of workable Placer Titles for the purposes of calculating work  0.65 0.85   This estimate compensates for overlap of staked claims, legacy leases and claim cells.
Estimated proportion of the 179 Mechanical Permits issued in 2005 for Claims & Leases 0.25 0.75   Estimated split (claim/lease) based on client interviews
Estimated average hourly rate for work performed on title $15 $20   Estimate based on client interviews
Placer Operations Categories        
Estimated Short Term Placer Operation in Days/Year 4 4   Majority (60%) of holders will exceed minimum work only when gold is found, market price is high and permitting is not onerous.
Estimated Medium Term Placer Operation in Days/Year 14 14   20% of Holders will likely work 2 weeks/year or more when gold found & price are high 
Estimated Long Term Placer Operation in Days/Year 24 24   15% will work 30 days/year or more when they have an established gold deposit
Estimated Mechanical Placer Operation in Days/Year 30 30   Mechanical Operations will likely work 30 days/year or more to offset their investment.
Estimated Hours Worked/Day for a Typical Placer Operation 6.5 8   This estimate is intended to allow for down time and set-up time.
Dimensions of Each Placer Category        
Estimated proportion of Placer Titles that are Short Term Operators 0.60 0.75   Estimate based on client interviews
Estimated Proportion of Placer Titles that are Medium Term Operators 0.25 0.10   Estimate based on client interviews
Estimated Proportion of Placer Titles that are Long Term Operators 0.15 0.15   Estimate based on client interviews
Cost to process cubic metre of placer material $50 $50   Mineral Titles Info Letter No 19.
Labour Applied to Each Category        
Estimated Average Labourers on a Short Term Placer Operation in 2005 1 1   Estimate based on client interviews
Estimated Average Labourers on a Medium Term Placer Operation in 2006 2 2   Estimate based on client interviews
Estimated Average Labourers on a Long Term Placer Operation in 2007 4 4   Estimate based on client interviews
Estimated Average Labourers Working on a Mechanical Placer Operation in 2008 6 10   Estimate based on client interviews
Operating Cost Applied to Each Category        
Estimated Accommodation & Travel Cost costs/day/person working a Placer Operation $50 $50   Estimate based on client interviews
Estimated Equipment Cost for Short Term Placer Operation. $500 $500   Estimate based on client interviews
Estimated Equipment Cost for Medium Term Placer Operation. $2,000 $2,000   Estimate based on client interviews
Estimated Equipment Cost for Long Term Placer Operation. $8,000 $8,000   Estimate based on client interviews
Estimated Equipment Cost for Mechanical Placer Operation. $10,000 $10,000   Estimate based on client interviews
Material Processing Costs for Each Category        
Estimated Cubic Metres of Placer material process on Short Term Operation in a year. 2 5   Estimate based on client interviews
Estimated Cubic Metres of Placer material process on Medium Term Operation in a year. 8 10   Estimate based on client interviews
Estimated Cubic Metres of Placer material process on Long Term Operation in a year. 50 70   Estimate based on client interviews
Estimated Cubic Metres of Placer material process on Mechanical Operation in a year. 1,500 2,000   Estimate based on client interviews
       
Table 3 - Estimated Value of Placer Activity in the Province Based on Three Estimate Models        
Title Administration Revenue        
Title Maintenance Fees $474,000 $1,454,500 $1,928,500  
Cash in Lieu Fees $250,000   $250,000  
Document Recording Fees $50,000 $12,000 $62,000  
Total Title Revenue $774,000 $1,466,500 $2,240,500  
Estimate 1 - Work Requirements        
Work Required According to MTA $2,370,000 $2,909,000 $5,279,000  
Estimate 2 - Operational Categories        
Number of Titles        
Number of Titles - Short Term Operations 2,073 106 2,179  
Number of Titles - Medium Term Operations 864 14 878  
Number of Titles - long Term Operations 518 21 539  
Number of Titles -  Mechanical Operations 45 134 179  
Number of Hectares        
Hectares in Short Term Operations 140,382 111,666 252,048  
Hectares-Medium Term Operations 58,492 14,889 73,381  
Hectares in Long Term Operations 35,095 22,333 57,429  
Hectares in Mechanical Operations 3,030 142,012 145,042  
Cost of Labour        
Labour Cost - Short Term Operations $808,529 $67,560 $876,089  
Labour Cost - Medium Term Operations $2,358,208 $63,056 $2,421,264  
Labour Cost - Long Term Operations $4,851,171 $324,288 $5,175,459  
Labour Cost - Mechanical  Operations $785,363 $6,444,000 $7,229,363  
 Labour Total $8,803,270 $6,898,904 $15,702,174  
Operating & Accommodation Costs        
Oper & Accom Costs - Short Term  $1,140,233 $58,059 $1,198,292  
Oper & Accom Costs- Medium Term  $1,814,006 $29,558 $1,843,564  
Oper & Accom Costs - Long Term  $4,249,958 $173,123 $4,423,080  
Oper & Accom Costs - Mechanical  $460,925 $1,409,625 $1,870,550  
 Oper & Accom Total $7,665,121 $1,670,364 $9,335,486  
Estimate 3 - Material Process Costs        
Cost to Process Cu Metres - Short Term  $207,315 $26,391 $233,706  
Cost to Process Cu Metres - Medium Term  $345,525 $7,038 $352,563  
Cost to Process Cu Metres - Long Term  $1,295,719 $73,894 $1,369,613  
Cost to Process Cu Metres - Mechanical  $3,356,250 $13,425,000 $16,781,250  
 Material Processing Total $5,204,809 $13,532,322 $18,737,131  
       
Table 4 -Economic Estimate Summary        
Estimate 1 - Work Requirement        
Work Requirement $5,279,000      
Mineral Titles Revenue $2,240,500      
Total $7,519,500      
Estimate 2 - Operational Categories        
Labour Costs $15,702,174      
Operating Costs $9,335,486      
Mineral Titles Revenue $2,240,500      
Total $25,037,660      
Estimate 3 - Material Processing Cost        
Material Processing Costs $18,737,131      
Mineral Titles Revenue $2,240,500      
Total $20,977,631